Comparison of Optimization Project Scheduling with Term Cost-Balancing by CPM-Earliest, CPM-Latest, and CPM-Monte Carlo Methods (Case of Housing Project Type 65) a) Universitas PGRI Ronggolawe Abstract The most effective and realistic project scheduling is the one which is able to integrate various aspects such as time, resources, and costs. Many scheduling methods to optimize time and cost have been introduced by researcher. The most widely used among those methods is Critical Path Method (CPM). In addition, the CPM method, namely CPM (Earliest) and CPM (Latest), can also be combined with other methods such as in previous studies using the CPM-Cuckoo Search (CS) and CPM-Monte Carlo (MC) methods in terms of optimize project scheduling with daily cost-balancing. Considering that the disbursement of project funds is actually carried out in a periodic manner, the researchers have to conduct research that is more realistic. The CPM method has been proven to optimize the project scheduling with term cost-balancing more effectively and efficiently than daily cost-balancing. This research will study how CPM-MC can optimize the term cost-balancing case and then compare the optimal value of the term cost-balancing of the type 65 housing project scheduling calculated by the CPM (Earliest), CPM (Latest), and CPM-MC methods. Keywords: Project Scheduling, Term Cost Balancing, CPM, Monte Carlo Topic: MATHEMATICS AND STATISTICS |
| ICMNS 2023 Conference | Conference Management System |